Contact us - +12567847275

Management

Q Consider a project having the following six activities:

Immediate Max Crash cost

Activity Predecessors Time (weeks) Crash* per week

A E, F 4 2 $2000

B A 6 2 $1000

C A, D 5 2 $1250

D F 3 2 $1000

E none 5 2 $500

F none 6 6 N/A

*Shortest possible time for the task

  1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

  1. List the tasks on the critical path

  1. What is the expected project duration in weeks?
  1. What is the slack for each activity?

A: B: C D: E: F:

  1. The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost? List the new duration of each task and any associated crash costs

Activity Duration Crash Cost

A

B

C

D

E

F

  1. Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

List the tasks on the critical path (0.4 pts.)

Solution:

15% off for this assignment.

Our Prices Start at $11.99. As Our First Client, Use Coupon Code GET15 to claim 15% Discount This Month!!

Why US?

100% Confidentiality

Information about customers is confidential and never disclosed to third parties.

Timely Delivery

No missed deadlines – 97% of assignments are completed in time.

Original Writing

We complete all papers from scratch. You can get a plagiarism report.

Money Back

If you are convinced that our writer has not followed your requirements, feel free to ask for a refund.